Construction has recently commenced on site at Flow Power’s Bennetts Creek Battery. To facilitate the major construction program, upgrades to
the road are required at the Monash Way (C456) entry point to the site. The approved roadworks will construct suitable access, including a left turn treatment.
The above map shows an indicative location of the works.

Monash Way works include:

  • Works are scheduled to commence from 25 May 2026 between the hours of 7am and 5pm, Monday to Saturday.
  • Traffic Management will be in place and there will be a temporary reduction to the speed limit.
  • There will be no lane closures during the works.
  • The works will be completed by 16 July 2026.

Keeping in Touch and Questions

If you would like to contact us about Bennetts Creek Battery, please get in touch via the details below. We can also add you to our newsletter, which is distributed periodically and features updates to the project and happenings on site.